Day-by-Day Pilot Plan

The pilot runs in five phases: a setup phase before Day 1, whose duration is driven by PortCo readiness rather than a fixed window, followed by the 40 working day diagnostic sprint (Day 1 to Day 40). The plan below shows the activities, deliverables and ownership by day. Decision gates at Day 15 and Day 40 punctuate the work and provide structured exit points.

The figures referenced as "expected outputs" in the table are illustrative for a £30M-spend PortCo. Adjust the £250K and £500K thresholds proportionally for larger or smaller candidates.

Phase 1, Setup
Before Day 1
Access, legal, stakeholders
Phase 2, Discovery
Day 1 to 15
Agents harvest, first findings
Phase 3, Validation
Day 16 to 30
HITL review, classify
Phase 4, Roadmap
Day 31 to 40
Prioritise, plan, deliver
Phase 5, Gates
Day 15 and 40
Sponsor decision points

40-Day Sprint, Workstream Timeline

Each bar represents one continuous workstream. The two red markers are the Day 15 Early Signal Gate and the Day 40 Go/No-Go Decision.
Workstream
D1D5 D10 D15 ▼ D20 D25 D30 D35 D40 ▼
Agent activation and discovery sweep
D1 to D10, harvest
Contract parsing and extraction
D3 to D17, all contracts processed
ERP cross-checking (Validation Agent)
D7 to D27, invoice variance detection
Inference and ownership tracing
D9 to D21, orphaned and inferred
Cross-entity comparison (Synergy Hunter)
D15 to D27, pricing harmonisation
Human-in-the-loop review (POC)
D8 to D35, continuous
Weekly sync with CFO sponsor
Day 15 Early Signal Gate
▼ Gate
Prioritisation and roadmap build
D30 to D40, roadmap
Value waterfall finalisation
D33 to D40, classify and quantify
Day 40 Go/No-Go Decision

Day-by-Day Activity Detail

Aggregated by week, with daily granularity around the decision gates. POC = Point of Contact (PortCo Procurement or Finance lead).
Day Phase Activity Output / Deliverable Owner
-10 to -2SetupLegal (NDA, DPA), Technical (M365, ERP, Entra ID access), Stakeholder (briefings)Readiness checklist signed offA&C Lead
-1SetupFinal readiness check, agent smoke testsGo/no-go for Day 0A&C Platform
0SetupHalf-day kickoff workshop, agents activatedPilot live, baseline extraction beginsA&C Lead
1 to 3DiscoveryCopilot Lens Agents sweep SharePoint, OneDrive, email per lens userDocument inventory, first contracts surfacedA&C Platform
3 to 5DiscoveryForensic Harvester begins contract parsing, version determinationFirst 100 to 200 contracts indexed in Trust LedgerA&C Platform
5SetupWeekly sync 1: progress, blockers, first observationsSync notesA&C Lead, CFO
5 to 8DiscoveryERP Connector full extract, entity resolution runningVendor master cleaned, invoice data loadedA&C Platform
8 to 10ValidationFirst Validation Agent passes against contracts vs invoicesFirst quantified findings appear in Trust LedgerA&C Platform
8 onwardsValidationPOC begins HITL review of findings as they accumulateValidated Value pool starts growingPOC
10SetupWeekly sync 2: early findings previewSync notes, sponsor expectation setA&C Lead, CFO
10 to 14DiscoveryRenewal Scheduler completes, auto-renewals identifiedAuto-renewal calendar, time-critical items flaggedA&C Platform
15GateEarly Signal Gate. £250K threshold check, sponsor review of Day 15 DashboardRight-to-continue decision, sign-off or early exitCFO, A&C Lead
15 to 18ValidationSynergy Hunter starts cross-entity comparisonPricing harmonisation findingsA&C Platform
18 to 22ValidationInference Agent completes ownership traces, orphaned contracts flaggedH7 findings, dependency mapA&C Platform
20SetupWeekly sync 3: validation rate, finding mixSync notesA&C Lead, CFO
22 to 27ValidationGhost Hunter completes licence-to-user matching, dormant accounts surfacedH5 tail spend findingsA&C Platform
25SetupWeekly sync 4: pre-roadmap view, value classification previewSync notes, draft value waterfallA&C Lead, CFO
27 to 30ValidationPOC validation push: clear backlog of high-confidence findings80%+ of high-confidence findings validatedPOC, A&C Lead
30 to 33RoadmapImpact Agent computes return-on-effort for every Actionable findingPrioritised action queue, P1 to P4A&C Platform
33 to 36RoadmapDependency Mapper checks each P1 to P2 action for operational riskSafe-to-act list of 5+ findingsA&C Platform
35SetupWeekly sync 5: roadmap draft reviewRoadmap iterated with sponsor inputA&C Lead, CFO
36 to 38RoadmapValue waterfall finalised: Identified, Validated, Actionable, Committed, Banked forecast. CFO assigns named owners and target dates for each Actionable finding.Five-stage waterfall, value-by-type split, named ownersA&C Lead, CFO
38 to 39RoadmapDay 40 deliverable assembled: dashboard, register, calendar, roadmap, audit logFull Day 40 packA&C Lead
40GateGo/No-Go Decision. Day 40 review with sponsor: £500K threshold across all five stages, 5+ safe actions, hypothesis coverage, Committed Value confirmedDecision: continuation engagement or close-outCFO, Operating Partner, A&C Lead
40+HandoverTrust Ledger handed to PortCo, raw data not retained by A&CAudit log export, ownership transferA&C Lead, POC